How can we run multiple manifests sequentially?

asked 2015-03-19 10:48:51 -0500

abhishekb gravatar image

I want to execute b.pp after execution of a.pp . How can i do that?

edit retag flag offensive close merge delete

1 Answer

Sort by ยป oldest newest most voted
0

answered 2015-03-25 15:37:49 -0500

WhatsARanjit gravatar image

updated 2015-03-25 15:39:22 -0500

Take a look at resource ordering. But probably something like this in your site.pp/nodes.pp:

class { 'module::a': }
class { 'module::b':
  require => Class['a'],
}

ref: https://docs.puppetlabs.com/learning/ordering.html